Implementation
This is your Services section. This is a great place to give more information about the services you provide. You can write a general description of what your business offers then add more details below.​This section can be adapted for your website.
Software installation
Water Scale Baster Energy Efficiency and Decarbonization Solution software is first downloaded in the workstation of the client.
Time Frame:1 day
Data Collection
Prior to Installation
After verifying the correct installation of IOT devices and connection to the program, the system starts to capture data from cooling tower before placing the Water Scale Blaster equipment.
Time frame: 30 days.
Equipment placement
Technical Service team place the equipment according to the cooling tower's capacity.
Time frame: 1 day.
Detached Water Scale Removal
After installing Water Scale Blaster for about 2-3 weeks, existing water scale will start to detach from cooling tower. Maintainance people will be needed to remove detached water scale.
Time frame: 2-3 weeks day.
Data Collection Post Installation
Data Analysis and Energy Efficiency Report
After installing Water Scale Blaster for about 2-3 weeks, existing water scale will start to detach from cooling tower. Maintainance people will be needed to remove detached water scale.
Time frame: 2-3 weeks